Project

General

Profile

Actions

Task #238

open

Task Group #191: [Dev] MoveIt Pro Application development

Task Group #237: [Dev-ATAG] Scalable Tactile Grasping System for Allegro Hand (ATAG)

[Dev-ATAG plan] Drafting and Reviewing the ATAG Development Plan

Added by Sanghoon Lee 20 days ago.

Status:
New
Priority:
Normal
Assignee:
Start date:
03/16/2026
Due date:
% Done:

0%

Estimated time:
Product Code:
uAi SW:

Description

Development Plan Drafting and Reviewing

Draft the ATAG development plan and conduct a review with Management to finalize the development plan.

Key decision points are:

  1. Should we continue with Allegro Hand for near-term milestone validation, or pivot earlier to Tesollo DG-5F?
  2. Should a hardware-independent interface be developed now to support both platforms, or deferred until after baseline approval?
  3. Once the platform decision is made, when will the required test equipment be available?

No data to display

Actions

Also available in: Atom PDF